Jun 10, 2018 05:51:57 PM Edited Jun 10, 2018 05:58:00 PM by Claudia S
If someone could offer some advice please.
Contractor accepted a project 2 years ago that would take 2-3 month.
Every month progress slows down. Most recent week in which work was completed the total time was less than an hour and then the last 3 weeks ZERO work.
Contactor is still in contact, but does no work on the project. Explanation is an increase in non-work commitments.
Any advice appretiated.
Thank you
Jun 10, 2018 06:14:27 PM by Preston H
This is your project. So it is YOUR timetable.
The reason it has taken this long is because you allowed it to take this long.
Had it been me, I would have hired about six different freelancers, and only continued working with the two best ones. If a freelancer got behind schedule, I would assign tasks to the others on the team. Or added new freelancers to the team as necessary to stay on schedule.