Aug 15, 2019 04:15:26 PM by Mary Elizabeth B
Hi. One of my projects is going more slowly than planned because the client has not been able to get the materials to me as quickly as she had hoped. I have already turned in some of the work, and we are still planning to proceed. Because now it will take much longer than planned to reach the first milestone, I was thinking about asking for partial payment of the first milestone ( calculated by percentage of work done.) Then the rest of the escrow could be released as the work was completed. But I was worried that partial payment of a milestone might have a negative impact on my JSS. If that is the case, I will just wait. Does anyone know?
Aug 15, 2019 04:19:46 PM by John K
Mary Elizabeth, partial payments are fine. Only total non-payment is harmful to JSS.